Main transmission lines completed
The main transmission projects completed by our companies or through partnerships in Special Purpose Entities (SPEs) in 2018 are:
-
230 kV transmission line Messias/Maceió II, with extension of 20 km (Alagoas) – Eletrobras Chesf
-
230/69 kV Maceió II Substation, with the installation of 02 transformers, 200 MVA each (Alagoas) - Eletrobras Chesf
-
230 kV transmission line Jardim / Nossa Senhora do Socorro, Double Circuit, 1.3 km long (Sergipe) - Eletrobras Chesf
-
230 kV Transmission Line Sectioning Jardim / Penedo, CS for connection in SE Nª.Sª. do Socorro, 5 km long (Sergipe) - Eletrobras Chesf
-
Substation Nossa Senhora do Socorro 230/69 kV, with the installation of 02 transformers, 100 MVA each (Sergipe) - Eletrobras Chesf
-
230 kV transmission line Eunápolis / Teixeira de Freitas II, Circuit 2, 152 km long (Bahia) - Eletrobras Chesf
-
Teixeira de Freitas II 230/138 kV Substation, with the installation of 03 autotransformers, 33.33 MVA each (Bahia) - Eletrobras Chesf
-
Santa Bárbara D'Oeste Substation 440 kV, with the installation of 01 static reactive compensator -300 / + 300 Mvar (São Paulo) - Eletrobras Furnas